GLENWOOD TRAILS 2030

FIVE-YEAR TRAIL DEVELOPMENT PLAN

Brief

The Orange Mountain Bike Club (OMBC) has engaged Advanced Trail Design to lead the next growth phase of the Glenwood State Forest trail network, with a focus on the precinct east of Boree Creek. Building on a network ATD has been involved with since its inception in 2019, the plan aims to increase routing options, provide skill progression for all riders, and keep the network adaptable around ongoing forestry harvesting operations.

The work supports the club's Glenwood Forest Precinct 5-Year Trail Development Strategy (2026–2031) and its Forestry Corporation of NSW access renewal, with the base plan to be presented to Forestry this year. Development costs are funded upfront by the club so they can be included in upcoming grant applications.

  • Location: Glenwood State Forest, Orange NSW

  • Client: Orange Mountain Bike Club

  • Land Manager: Forestry Corporation of NSW (FCNSW)

  • Standards: Australian Mountain Bike Trail Building Guidelines and IMBA sustainable trail design principles

  • Scope: Approximately 19,500 m of new trail

Proposed new trails include:

  • Trail of Awesomeness: 1,200 m of new sections to replace harvested sections

  • East Easy Climb: 7,500 m

  • East Easy/Intermediate Descent: 5,800 m

  • East Intermediate Descent: 3,300 m

  • East Difficult Descent: 1,700 m

Club requirements:

  • Comprehensive trail plans and mapping, with ground truthing

  • A detailed build budget (project management and trail works) plus ongoing maintenance projections

  • A recommended execution model

  • Year-on-year participation data (2021, 2023 and 2025) to demonstrate growth and value for money in grant applications

Delivery stages:

  • Stage 1 – Concept Design, Budgeting & Participation Analysis: spatial concept alignments, build and maintenance costings, and participation reporting for Forestry approvals and grant submissions.

  • Stage 2 – Detailed Design, Ground Truthing & Flagging: final field alignments, on-ground flagging and GIS construction data for trail builders.

Reference: Glenwood Forest Precinct 5-Year Trail Development Strategy (OMBC, PDF)

Terrain Analysis

The terrain at Glenwood State Forest was analysed using a high-resolution 1 m LiDAR ground model (2024) and GIS software to identify the best locations for new trails. Key factors included elevation, side slope, watercourses, ecological and heritage values, existing trails and fire roads, and the Forestry Corporation of NSW harvesting schedule.

The project area spans roughly 440 m of elevation, from the bottom trailhead at 789 m to the West Peak high point at 1,228 m, giving plenty of vertical for new descending trails and the climbing routes that serve them.

Satellite imagery

Satellite imagery, together with local knowledge of the forest, was used to identify tree cover, the existing fire road network, recently harvested blocks and other features to avoid or work with.

Glenwood is predominantly a pine plantation managed by Forestry Corporation of NSW, with ribbons of native vegetation along the creek lines and forest edges. Pine canopy provides good shade and keeps grass off the trails, but plantation blocks are periodically thinned and clear felled, so trail placement needs to account for the harvesting cycle (see Harvesting Schedule below).

The fire road network provides access for construction and maintenance, and gives logical start and finish points for new trails.

Height mapping

Elevation ranges from 789 m at the bottom trailhead on the northern boundary to 1,228 m at the West Peak high point in the south, a difference of roughly 440 m. The East Peak reaches 1,162 m, and the Gravity Event Centre sits near the middle of the forest at 890 m.

The ground generally falls from the two southern peaks towards the creek and the northern trailhead, giving long, consistent fall lines suited to descending trails, with the eastern precinct offering the greatest relief for the proposed East descents and climb.

Side slope mapping

Uses colour coding to indicate suitability for trail placement based on the “half rule” of sustainable trail design, which recommends that a trail’s gradient not exceed half of the side slope’s grade. Areas under 10% side slope are generally avoided due to poor drainage, areas exceeding 40% become progressively more expensive to construct, and slopes above 60% can become unstable and difficult to build on.

  • Green (10–20%): suited to easy trails and climbing routes

  • Blue (20–40%): ideal for intermediate descending trails

  • Black (40–60%): difficult trails and technical features

  • Red (60–100%): extreme terrain, avoided or used sparingly

The northern and central parts of the forest are relatively gentle, with large areas under 20% that suit easy trails and climbs. The steepest ground is concentrated on the north-facing slopes below the East Peak and along the southern ridgelines, where long bands of 20–60% side slope provide the best terrain for the proposed East intermediate and difficult descents.

Ecological and heritage constraints

Government ecological and heritage datasets were overlaid on the site to identify areas that trails should avoid or treat with care. Values were grouped by priority:

  • A – Avoid: Mt Canobolas State Conservation Area (NPWS) / LEP heritage item along the south-eastern boundary, and Biodiversity Values Map land along the main creek corridor.

  • B – Minimise impact: Mt Canobolas Grassy Forest and Rockplate Shrubland communities, and creek-flat / Ribbon Gum woodland (possible threatened ecological community).

  • C – Consider: remnant native vegetation patches mapped within and around the forest edges.

The main creek is mapped as key fish habitat, so new crossings will need bridges. The whole forest is Bush Fire Prone Land. No State Heritage, Aboriginal Place or other listed heritage items are mapped inside the boundary; AHIMS and BioNet searches are pending. Trail alignments will also follow the REF requirements protecting the Silver-leaf Candlebark, Prostanthera gilesii and the Mt Canobolas Xanthoparmelia lichen community, and bike wash stations will continue to limit the spread of Phytophthora.

Harvesting schedule

Glenwood is a working pine plantation, so the Forestry Corporation of NSW harvesting cycle has a major influence on where and when new trails can be built. Pine age class data from FCNSW was mapped to show each block's status in 2027, based on thinning at around 15 years after planting and clear felling at around 30 years.

  • Planted less than 2 years ago: too early, wait before building

  • 2–13 years: good for building

  • 13–17 years: thinning due, trails will be affected

  • 17–27 years: good for building

  • 28+ years: clear fell due

Most of the forest is in the 2–13 and 17–27 year classes, giving a long window for new trails. Recently replanted blocks in the north are best avoided for now, and the block at the north-eastern corner is due for clear felling. Sections of the Trail of Awesomeness lost to harvesting will be replaced with around 1,200 m of new trail, and the strategy notes the TOA trailhead remains at risk of logging within five years.

Terrain overview

  • LiDAR DEM Source: Glenwood LiDAR ground model (Advanced Trail Design)

  • Date: 2024

  • Resolution: 1m

  • Highest point: 1,228m (West Peak)

  • Lowest point: 789m (bottom trailhead)

  • Elevation Difference: 439m

  • Side Slope: 0–100%, with most of the steeper descending terrain in the 20–60% range

  • Land Manager: Forestry Corporation of NSW (pine plantation, harvested on a ~30-year cycle)

  • Key constraints: Mt Canobolas SCA boundary, creek corridors (bridge crossings), native vegetation remnants and the harvesting schedule

DESIGN

The concept design takes the findings of the brief and the detailed terrain analysis, together with local knowledge of the forest, and combines them with industry best practice for engaging and sustainable trails. The result is a proposal that grows the Glenwood network while keeping it adaptable around Forestry harvesting operations.

In East Glenwood, four new trails would add about 14.6 km of trail, so riders still have a network when the west of the forest is closed for harvesting. In West Glenwood, existing trails would be improved and better linked: an easier Cut It Out descent, new links to the Gravity Centre and True Blue, and a rebuilt Trail of Awesomeness loop.

MAP

  • Click each item for more details.

Next Steps..

With the terrain analysis complete, initial trail plotting is now under way. Draft alignments for the approximately 19,500 m of new trail are being placed to suit the terrain – using the height and side slope mapping to set sustainable gradients and good flow – while working around the ecological and heritage constraints and fitting within the Forestry Corporation of NSW harvesting schedule, so new trails sit in blocks that will remain available for riding.

The draft trail plan will then be used to prepare construction cost estimates and ongoing maintenance projections, and to support trail approvals with Forestry Corporation of NSW as part of the club's access renewal, along with OMBC's upcoming grant applications.